TC Light & Power To Start Tree/Vegetation Clearing Project Next Week

By Beth Milligan | Nov. 30, 2021

A tree contractor for Traverse City Light & Power, Asplundh Tree Expert Co., will start a tree and vegetation clearing project on Monday, December 6.

The project will take place along the railroad corridor from Barlow Street to Airport Access Road in preparation for a transmission line upgrade project planned to begin in April 2022 (pictured, project map). The work is expected to be completed by Friday, December 31. Staff will put up warning signs along the walking path at both Rose and Barlow streets and all streets in between, though the TART Trail will remain open in the area. Spotters will be used to “aid in traffic control and pedestrian control to assure the public is safe during the work,” according to staff documents, with other work completed using bucket trucks and wheel feed chippers.

The mower that will be used on the site has a trap door on the front to deflect debris downward instead of forward, “keeping flying debris to a minimum.” While the project could be visually impactful – staff photos of similar line maintenance projects show wide ground clearance around lines ranging from 20-100 feet, as well as a broad aerial buffer – the project also calls for a restoration component to include planting native shrubs such as highbrush cranberry, blackhaw viburnum, and common lilac.

The upgrade project will involve rebuilding 2.71 miles of existing electric transmission line to improve capacity and increase grid reliability. TCL&P will be bringing the right-of-way back to industry standard clearances “in order to ensure the safe and reliable operation of the utility lines,” according to a utility release. According to staff documents, approximately half of the utility’s 13,000 customers are serviced by the transmission line, and a substation fed by the line is the main backup feed for all of downtown. The distribution circuit is also the main backup feed for the airport industrial park and the air traffic control tower. Without maintenance, there are several public safety risks related to the line, including downed high voltage lines, sparks from trees contacting energized lines, and stray voltages, according to staff documents.

Comment

The Story Of NMC's Mobile Food Pantry

Read More >>

Traverse City's Accidentals Appear On The CMA Awards

Read More >>

Traverse City Mural Festival Planned for 2025

Read More >>

GT County Commissioners Eye 2025 Budget, Including New Positions & Projects

Read More >>

Interest Rates Rise, But So Do Northern Michigan Home Prices

Read More >>

North Ed Launches Survey To Inform Superintendent Search

Read More >>

Let It Snow: Local Ski Resorts Hoping For A Comeback Season After 2024's Dire Winter

Read More >>

Cherryland Center Owners Work Toward Updated Mall Plan as New Businesses Come Online

Read More >>

The Magical World of Holiday Art Markets

Read More >>

Housing Support, Project Alpha, ARPA Funding on County Agenda

Read More >>

Two-Way Streets, Rotary Square, Riverfront, TART Trail Emerge as Early Contenders for Remaining TIF 97 Funds

Read More >>

Central United Methodist Responds to Graffiti, Affirms Trans/Immigrant Support

Read More >>

Made in Michigan: Yana Dee's Journey

Read More >>

2024 Holiday Gift Guide Deadline Is This Week

Read More >>